Do you have a project and need a container quickly? Whether it’s a standard container, a pre-modified model ready for delivery (Featured Product), or a fully customized container, delivery time varies significantly.
Many customers assume that a custom-modified container can be ready in just a few days. However, the more customization involved, the longer the process takes. Between design, technical adjustments, and manufacturing, a custom project requires careful planning.
In this article, you’ll discover the real delivery times for each type of container, why certain modifications take longer, and how to anticipate your project timeline to avoid unexpected delays.
If you need a container without modifications, this is the fastest option. Standard containers (20 feet, 40 feet, high cube, etc.) are generally in stock and ready for delivery.
💡 Tip: If you’re on a tight schedule, it’s best to reserve your container as soon as possible to avoid delays due to availability or transportation.
If you need a container that has already been modified with common improvements (such as extra doors, insulation, a basic electrical system, or windows), you can opt for one of our Featured Products.
Featured Products are containers modified with the most requested features by our customers. Since these models are pre-modified in advance, they are almost always in stock and available for fast delivery.
💡 Tip: If you need a modified container quickly, ask for the list of Featured Products currently available. You may find an option that meets your needs without additional modifications.
If you need a fully customized container, be prepared for a longer wait. Unlike Featured Products, which are pre-modified and ready to ship, a custom container requires detailed planning, specific adjustments, and manufacturing time.
We officially commit to a delivery date only when the final manufacturing plans are approved (signed off by the client). Before this step, we are still in the design and development phase, making it difficult to provide a precise timeline.
💡 Tip: Plan ahead! If you’re in a hurry, talk to our experts to see if a Featured Product can be quickly adapted to your needs.
If you’re considering a custom-modified container, proper planning is crucial to avoid delays and optimize timelines.
The clearer your requirements, the faster the design phase. Think about:
💡 Tip: A well-defined project from the beginning prevents unnecessary back-and-forth discussions and speeds up plan approval.
The design phase can take 1 to 4 weeks, or longer for complex projects. Any delay in approving the plans results in a delay in manufacturing.
💡 Tip: The faster you approve the plans, the sooner we can start production.
Under normal conditions, manufacturing takes 4 to 8 weeks, but during high demand, it can extend to 16 weeks. If you have a fixed deadline (event, construction project, relocation), it’s essential to place your order in advance.
💡 Tip: Order several months ahead if you want to avoid peak season delays.
Before the manufacturing plans are signed off, we cannot guarantee a specific delivery date.
💡 Tip: Don’t schedule your project based on an estimated timeline before plan approval.
📌 Delivery time summary by container type:
If you have an urgent need, check the availability of Featured Products, which offer a quick and ready-to-use solution. If you need a custom container, plan your project well in advance to avoid frustration due to delays.
💡 Need a container quickly? Contact us now to check available models!